WMRA CELEBRATES GROUND BREAKING

West Michigan Regional Airport celebrated the ground breaking of the new Airport Office Business Center & Aircraft Apron Area project on Monday, September 21, 2015. Beginning with a flyover, five future pilots exited Metal Flow's jet and welcomed the audience. The...

read more

WEEKS 4 AND 5 OF WMRA CONSTRUCTION SITE

Week 4:  September 7 - 12 The construction crew continued earthwork balancing on both the Landside and Airside. The building pad was completed. Week 5:  September 14 - 19 On September 15 Mead & Hunt was on site to stake building corners, the south detention pond,...

read more

WEEK 3 OF WMRA CONSTRUCTION SITE

WEEK 3:  August 31 - September 5  This week the earthwork will continue with the emphasis on building pad. The completion of the pad is expected by September 11. Also, preparation for the underground pipe work will begin.      