WEEK 8: October 5-10 Site Improvements Completed under-drain in the parking lot and apron Began installation of Geotextile fabric on apron Began installation sand sub-base for parking lot and apron Building Completed pouring foundation Continued pouring concrete...
WEEKS 8-9 OF WMRA CONSTRUCTION SITE