Monthly Archives: October 2015

WEEKS 8-9 OF WMRA CONSTRUCTION SITE

WEEK 8:  October 5-10
Site Improvements
Completed under-drain in the parking lot and apron
Began installation of Geotextile fabric on apron
Began installation sand sub-base for parking lot and apron
Building
Completed pouring foundation
Continued pouring concrete walls

WEEK 9: October 12-17
Site Improvements
Completed sub-base installation for parking lot and apron
Began installation of aggregate base
Electrical work began
Building
Poured remaining concrete walls
Began underground plumbing
Began back […]

WEEKS 6-7 OF WMRA CONSTRUCTION SITE

WEEK 6: September 21 – 26
Site improvements:
Completed storm sewer work
Installed under-drain in the parking lot and began working in apron under-drain
Installed weir structure for south detention pond
Building:
Began pouring concrete footings
Began pouring concrete walls

WEEK 7:  September 28 – October 10
Site improvements:
Poured remaining concrete walls
Building:
Completed under-drain installation for apron
Installed stabilizing fabric for apron sub-grade
Installed the first […]

WINGS OF MERCY CAREAFFAIRE 2015

The Wings of Mercy CareAffaire held on August 22, 2015 was the most well attended event yet! Over 650 pancake breakfasts were served by our local Lions Club! Young Eagles free flights for kids ages 8-17 totaled 100! Over $31,000 was donated to Wings of Mercy!

Thanks especially to Grace of Wings of Mercy who […]