WEEKS 18-19: December 7 - December 19 BUILDING Continue with steel stud walls and sheeting Install roof drains Begin installation of membrane roof Begin work on brick and window frames
WEEKS 18-19 WMRA CONSTRUCTION SITE
read more
WEEKS 18-19: December 7 - December 19 BUILDING Continue with steel stud walls and sheeting Install roof drains Begin installation of membrane roof Begin work on brick and window frames