Monthly Archives: April 2016

WEEKS 36-37 WMRA CONSTRUCTION SITE

WEEKS 36-37:  April 11 – April 23
BUILDING
Continued HVAC, electrical and plumbing
Began siding
Began acoustic ceiling grid
Continue metal siding
Finish tile

SITE
Installed sub-base for cul-de-sac
Install aggregate
Continued paving concrete on apron
Sidewalk prep

WEEKS 34-35 WMRA CONSTRUCTION SITE

WEEKS 34-35:  March 28 – April 9
BUILDING
Continue HVAC, electrical work, plumbing
Start bathroom tile
Masonry work
Continue framing ceiling and installing ceiling grid
Installed bathroom cabinets and counters
Formed stairs and ramp and ran snow melt piping
Poured concrete for stairs and ramp
Finished hanging drywall and fireplace drywall

SITE IMPROVEMENTS
Continue excavation for cul-de-sac
Underdrain placement in cul-de-sac
Paved concrete on apron
Continued standing light […]

WEEKS 32-33 WMRA CONSTRUCTION SITE

WEEKS 32-33:  March 14 – March 26
BUILDING
Continued HVAC and electrical
Continued drywall finishing
Continued priming/painting
Continued framing wood ceiling panels

SITE IMPROVEMENTS
Continued fine grading the apron
Poured parking lot and apron light bases