fbpx

Month: April 2016

WEEKS 36-37 WMRA CONSTRUCTION SITE

WEEKS 36-37:  April 11 – April 23 BUILDING Continued HVAC, electrical and plumbing Began siding Began acoustic ceiling grid Continue metal siding Finish tile SITE Installed sub-base for cul-de-sac Install aggregate Continued paving concrete on apron Sidewalk prep

read more

WEEKS 34-35 WMRA CONSTRUCTION SITE

WEEKS 34-35:  March 28 - April 9 BUILDING Continue HVAC, electrical work, plumbing Start bathroom tile Masonry work Continue framing ceiling and installing ceiling grid Installed bathroom cabinets and counters Formed stairs and ramp and ran snow melt piping Poured...

read more

WEEKS 32-33 WMRA CONSTRUCTION SITE

WEEKS 32-33:  March 14 – March 26 BUILDING Continued HVAC and electrical Continued drywall finishing Continued priming/painting Continued framing wood ceiling panels SITE IMPROVEMENTS Continued fine grading the apron Poured parking lot and apron light bases

read more