WEEKS 36-37: April 11 – April 23 BUILDING Continued HVAC, electrical and plumbing Began siding Began acoustic ceiling grid Continue metal siding Finish tile SITE Installed sub-base for cul-de-sac Install aggregate Continued paving concrete on apron Sidewalk prep
WEEKS 36-37 WMRA CONSTRUCTION SITE