WEEKS 44-45: June 6 – June 18 BUILDING Continued HVAC, electrical and plumbing Complete cabinets Complete installation of carpet Complete epoxy floor Complete painting Begin floor mats Install ramp railing Install glass door sidelights SITE Began P-501 repairs...