WEEKS 30-31 WMRA CONSTRUCTION SITE

WEEKS 30-31:  February 29 – March 12
BUILDING
Continue drywall installation
Continue masonry
Continue HVAC and electrical
Install Suntuitive Glass
Continue electrical work
Installed fireplace
 

2016 WINGS OF MERCY CAREAFFAIRE

Please join us on Saturday, August 27, 8:00 a.m. – 12 noon for the 2016 Holland Wings of Mercy CareAffaire at West Michigan Regional Airport.

To register for the Wings of Mercy Runway 5K, use the following link:
Wings of Mercy

Family fun include a fly-in, delicious pancake breakfast, Young Eagles Program offering kids ages 8-17 a […]

ENERGY SAVING WINDOWS BEING INSTALLED AT WMRA

Pleotint, whose corporate  headquarters and manufacturing are located in Jension, is all about saving energy. The low-e glass which allows visible light to pass through while controlling the passage of solar heat is now being installed at the new WMRA Business Center. The company’s Suntuitive brand of thermochromic self-tinting film is an inner layer […]

WEEKS 28-29 WMRA CONSTRUCTION SITE

WEEKS 28-29:  February 15-27, 2016
BUILDING
Completed insulation and steel framing
Installed permanent power
Installed fireplace
Began gypsum board and drywall installation and masonry
Continued electrical work, plumbing and HVAC

(photo above includes WMAA Building & Development Committee members and representatives from Mead & Hunt, Progressive AE and CL Construction)

Committee Tours New Business Center

The WMAA Building & Development Committee toured the new Airport Business Center. Committee members were excited to see the progress made. To date the roofing has been completed including the plumbing, electrical rough-in and steel stud walls. Semco installed gas service and the BPW installed power to the building. Check the WMRA website weekly […]

WEEKS 26-27 WMRA CONSTRUCTION SITE

WEEKS 26-27:  February 1-13, 2016
BUILDING
Completed roofing
North and east windows installed
Completed plumbing and electrical rough-in
Semco installed gas service
BPW installed power to building
Completed steel stud walls
Begin exterior wall insulation

 

WEEKS 24-25 WMRA CONSTRUCTION SITE

WEEKS 24-25:  January 18-25, 2016
BUILDING
Completed roof
Completed roof drains
Poured concrete for fireplace wall
Finished plumbing and electrical rough in
Continued installation of window frames and windows
Begin HVAC and installation of glass
Install cable from transformer pad to building

WEEKS 22-23 WMRA CONSTRUCTION SITE

WEEKS 22-23:  January 4-16, 2016
BUILDING
Completed exterior and interior steel stud installation
Completed sheeting
Completed roofing for upper roof
Continued roofing for lower roof
Continued installation of window frames
Began mechanical, plumbing and electrical rough-in

WEEKS 20-21 WMRA CONSTRUCTION SITE

WEEKS 20-21:  December 21 – January 2, 2016
BUILDING
Finished exterior walls
Continue interior steel stud walls and sheeting
Installed roof penetration
Began installation of membrane roof
Began window frame installation
Began mechanical, plumbing and electrical rough-in

 

WEEKS 18-19 WMRA CONSTRUCTION SITE

WEEKS 18-19:  December 7 – December 19
BUILDING
Continue with steel stud walls and sheeting
Install roof drains
Begin installation of membrane roof
Begin work on brick and window frames