WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more

Entryway Improvements at West Michigan Regional Airport

Because of the airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area was needed. The former airport terminal building at the entrance of Geurink Boulevard has served its purpose and is scheduled for demolition...

read more

EAST TAXIWAY CONNECTOR PROJECT

Construction is now underway and should take approximately two weeks to complete. The benefits the East Taxiway Connector project brings is to provide direct access from the Taxiway to the new Apron and is designed to improve overall traffic flow to the Airport...

read more

New Airport Business Center & Aircraft Apron Facts

Building: 7,500 square feet. The former office building was less than 2,000 square feet. Beautiful lobby and reception area furnished by Herman Miller. Main conference room furnished by Haworth, including glass walls. Pilot’s lounge furnished by Haworth, including...

read more

WEEKS 50-52 WMRA CONSTRUCTION

LAST WEEKS 50-52:  July 18 - August 6 BUILDING Installed lighting inverter Worked on antenna tower base Finish antenna installation Closeout documents SITE Punch list items        

read more

WEEKS 46-49 WMRA CONSTRUCTION SITE

WEEKS 46-49: June 20 – July 16 BUILDING Begin installation of radio tower Waiting for furniture Waiting for lighting inverter SITE Completed striping Completed fence installation        

read more

WEEKS 44-45 WMRA CONSTRUCTION SITE

WEEKS 44-45: June 6 – June 18 BUILDING Continued HVAC, electrical and plumbing Complete cabinets Complete installation of carpet Complete epoxy floor Complete painting Begin floor mats Install ramp railing Install glass door sidelights SITE Began P-501 repairs...

read more

WEEKS 42-43 WMRA CONSTRUCTION SITE

WEEKS 42-43: May 23 - June 4 BUILDING Continued HVAC, electrical and plumbing Began fin tube cabinets Installed carpet Complete painting Continued installing cabinets Complete metal siding Installed more plumbing fixtures Installed upper cabinets Completed snow melt...

read more

WEEKS 40-41 WMRA CONSTRUCTION SITE

WEEKS 40-41: May 9 – 21 BUILDING Continued HVAC, electrical and plumbing Continued metal siding Continued installing cabinets Completed window flashing Installed bathroom fixtures Installed acoustic ceiling tiles Completed flag poles Installed snowmelt in north...

read more

WEEKS 38-39 WMRA CONSTRUCTION SITE

WEEKS 38-39: April 25 – May 7 BUILDING Began window flashing Continued HVAC, electrical and plumbing Continued metal siding Continued cabinet installation Continued painting Completed acoustical ceiling grid Completed ceiling clouds Installed snowmelt in north...

read more