WEEKS 40-41: May 9 – 21 BUILDING Continued HVAC, electrical and plumbing Continued metal siding Continued installing cabinets Completed window flashing Installed bathroom fixtures Installed acoustic ceiling tiles Completed flag poles Installed snowmelt in north...
Projects
WEEKS 38-39 WMRA CONSTRUCTION SITE
WEEKS 38-39: April 25 – May 7 BUILDING Began window flashing Continued HVAC, electrical and plumbing Continued metal siding Continued cabinet installation Continued painting Completed acoustical ceiling grid Completed ceiling clouds Installed snowmelt in north...
WEEKS 36-37 WMRA CONSTRUCTION SITE
WEEKS 36-37: April 11 – April 23 BUILDING Continued HVAC, electrical and plumbing Began siding Began acoustic ceiling grid Continue metal siding Finish tile SITE Installed sub-base for cul-de-sac Install aggregate Continued paving concrete on apron Sidewalk prep
WEEKS 34-35 WMRA CONSTRUCTION SITE
WEEKS 34-35: March 28 - April 9 BUILDING Continue HVAC, electrical work, plumbing Start bathroom tile Masonry work Continue framing ceiling and installing ceiling grid Installed bathroom cabinets and counters Formed stairs and ramp and ran snow melt piping Poured...
WEEKS 32-33 WMRA CONSTRUCTION SITE
WEEKS 32-33: March 14 – March 26 BUILDING Continued HVAC and electrical Continued drywall finishing Continued priming/painting Continued framing wood ceiling panels SITE IMPROVEMENTS Continued fine grading the apron Poured parking lot and apron light bases
WEEKS 30-31 WMRA CONSTRUCTION SITE
WEEKS 30-31: February 29 - March 12 BUILDING Continue drywall installation Continue masonry Continue HVAC and electrical Install Suntuitive Glass Continue electrical work Installed fireplace
WEEKS 28-29 WMRA CONSTRUCTION SITE
WEEKS 28-29: February 15-27, 2016 BUILDING Completed insulation and steel framing Installed permanent power Installed fireplace Began gypsum board and drywall installation and masonry Continued electrical work, plumbing and HVAC (photo above includes WMAA Building...
WEEKS 26-27 WMRA CONSTRUCTION SITE
WEEKS 26-27: February 1-13, 2016 BUILDING Completed roofing North and east windows installed Completed plumbing and electrical rough-in Semco installed gas service BPW installed power to building Completed steel stud walls Begin exterior wall insulation
WEEKS 24-25 WMRA CONSTRUCTION SITE
WEEKS 24-25: January 18-25, 2016 BUILDING Completed roof Completed roof drains Poured concrete for fireplace wall Finished plumbing and electrical rough in Continued installation of window frames and windows Begin HVAC and installation of glass Install cable from...
WEEKS 22-23 WMRA CONSTRUCTION SITE
WEEKS 22-23: January 4-16, 2016 BUILDING Completed exterior and interior steel stud installation Completed sheeting Completed roofing for upper roof Continued roofing for lower roof Continued installation of window frames Began mechanical, plumbing and electrical...
WEEKS 20-21 WMRA CONSTRUCTION SITE
WEEKS 20-21: December 21 - January 2, 2016 BUILDING Finished exterior walls Continue interior steel stud walls and sheeting Installed roof penetration Began installation of membrane roof Began window frame installation Began mechanical, plumbing and electrical...
WEEKS 18-19 WMRA CONSTRUCTION SITE
WEEKS 18-19: December 7 - December 19 BUILDING Continue with steel stud walls and sheeting Install roof drains Begin installation of membrane roof Begin work on brick and window frames