Committee Tours New Business Center

The WMAA Building & Development Committee toured the new Airport Business Center. Committee members were excited to see the progress made. To date the roofing has been completed including the plumbing, electrical rough-in and steel stud walls. Semco installed gas...

read more

WEEKS 26-27 WMRA CONSTRUCTION SITE

WEEKS 26-27:  February 1-13, 2016 BUILDING Completed roofing North and east windows installed Completed plumbing and electrical rough-in Semco installed gas service BPW installed power to building Completed steel stud walls Begin exterior wall insulation  

read more

WEEKS 24-25 WMRA CONSTRUCTION SITE

WEEKS 24-25:  January 18-25, 2016 BUILDING Completed roof Completed roof drains Poured concrete for fireplace wall Finished plumbing and electrical rough in Continued installation of window frames and windows Begin HVAC and installation of glass Install cable from...

read more

WEEKS 22-23 WMRA CONSTRUCTION SITE

WEEKS 22-23:  January 4-16, 2016 BUILDING Completed exterior and interior steel stud installation Completed sheeting Completed roofing for upper roof Continued roofing for lower roof Continued installation of window frames Began mechanical, plumbing and electrical...

read more

WEEKS 20-21 WMRA CONSTRUCTION SITE

WEEKS 20-21:  December 21 - January 2, 2016 BUILDING Finished exterior walls Continue interior steel stud walls and sheeting Installed roof penetration Began installation of membrane roof Began window frame installation Began mechanical, plumbing and electrical...

read more

WEEKS 18-19 WMRA CONSTRUCTION SITE

WEEKS 18-19:  December 7 - December 19 BUILDING Continue with steel stud walls and sheeting Install roof drains Begin installation of membrane roof Begin work on brick and window frames

read more

WEEKS 16-17 WMRA CONSTRUCTION SITE

WEEKS 16-17:  November 23 - December 5 SITE IMPROVEMENTS Begin and complete water main installation Complete installation of P-209 aggregate base Begin on cul-de-sac area BUILDING Continued steel erection Continue steel stud walls Begin steel sheeting Begin steel...

read more

WEEKS 14-15 WMRA CONSTRUCTION SITE

WEEK 14:  November 9-14 Site Improvements Continued on sanitary sewer installation Worked on compaction of the sub-base material for the apron Began restoration of areas requiring MDOT roadside mix Building Continued steel construction WEEK 15: November 16-21 Site...

read more

WEEKS 12-13 WMRA CONSTRUCTION SITE

WEEK 12:  October 26-31 Site Improvements Continued installation of geotextile fabric on apron, and installation of sand sub-base and aggregate base Grading and compacting aggregate base for parking lot Building Completed underground plumbing, electrical and HVAC...

read more

WHEELS UP LANDS AT WMRA

Wheels Up Goes Pink is the motto Wheels Up (a charter company) is using for Breast Cancer Awareness. David Darcey, pilot of the pink aircraft, stopped at West Michigan Regional Airport for a scheduled charter flight. We found out that on October 1, 2015, in...

read more

WEEKS 10-11 WMRA CONSTRUCTION SITE

WEEK 10:  October 19-24 Site Improvements Continued installing geotextile fabric on apron, and installing sand sub-base and aggregate base. Continued installing sand sub-base and aggregate base for parking lot. Poured transformer pad for BPW transformer. Poured Weir...

read more

WEEKS 8-9 OF WMRA CONSTRUCTION SITE

WEEK 8:  October 5-10 Site Improvements Completed under-drain in the parking lot and apron Began installation of Geotextile fabric on apron Began installation sand sub-base for parking lot and apron Building Completed pouring foundation Continued pouring concrete...

read more