WEEKS 18-19: December 7 - December 19 BUILDING Continue with steel stud walls and sheeting Install roof drains Begin installation of membrane roof Begin work on brick and window frames
Blog
WEEKS 16-17 WMRA CONSTRUCTION SITE
WEEKS 16-17: November 23 - December 5 SITE IMPROVEMENTS Begin and complete water main installation Complete installation of P-209 aggregate base Begin on cul-de-sac area BUILDING Continued steel erection Continue steel stud walls Begin steel sheeting Begin steel...
WEEKS 14-15 WMRA CONSTRUCTION SITE
WEEK 14: November 9-14 Site Improvements Continued on sanitary sewer installation Worked on compaction of the sub-base material for the apron Began restoration of areas requiring MDOT roadside mix Building Continued steel construction WEEK 15: November 16-21 Site...
WEEKS 12-13 WMRA CONSTRUCTION SITE
WEEK 12: October 26-31 Site Improvements Continued installation of geotextile fabric on apron, and installation of sand sub-base and aggregate base Grading and compacting aggregate base for parking lot Building Completed underground plumbing, electrical and HVAC...
WHEELS UP LANDS AT WMRA
Wheels Up Goes Pink is the motto Wheels Up (a charter company) is using for Breast Cancer Awareness. David Darcey, pilot of the pink aircraft, stopped at West Michigan Regional Airport for a scheduled charter flight. We found out that on October 1, 2015, in...
WEEKS 10-11 WMRA CONSTRUCTION SITE
WEEK 10: October 19-24 Site Improvements Continued installing geotextile fabric on apron, and installing sand sub-base and aggregate base. Continued installing sand sub-base and aggregate base for parking lot. Poured transformer pad for BPW transformer. Poured Weir...
WEEKS 8-9 OF WMRA CONSTRUCTION SITE
WEEK 8: October 5-10 Site Improvements Completed under-drain in the parking lot and apron Began installation of Geotextile fabric on apron Began installation sand sub-base for parking lot and apron Building Completed pouring foundation Continued pouring concrete...
WEEKS 6-7 OF WMRA CONSTRUCTION SITE
WEEK 6: September 21 - 26 Site improvements: Completed storm sewer work Installed under-drain in the parking lot and began working in apron under-drain Installed weir structure for south detention pond Building: Began pouring concrete footings Began pouring concrete...
WINGS OF MERCY CAREAFFAIRE 2015
The Wings of Mercy CareAffaire held on August 22, 2015 was the most well attended event yet! Over 650 pancake breakfasts were served by our local Lions Club! Young Eagles free flights for kids ages 8-17 totaled 100! Over $31,000 was donated to Wings of Mercy! Thanks...
WMRA CELEBRATES GROUND BREAKING
West Michigan Regional Airport celebrated the ground breaking of the new Airport Office Business Center & Aircraft Apron Area project on Monday, September 21, 2015. Beginning with a flyover, five future pilots exited Metal Flow's jet and welcomed the audience. The...
WEEKS 4 AND 5 OF WMRA CONSTRUCTION SITE
Week 4: September 7 - 12 The construction crew continued earthwork balancing on both the Landside and Airside. The building pad was completed. Week 5: September 14 - 19 On September 15 Mead & Hunt was on site to stake building corners, the south detention pond,...
WEEK 3 OF WMRA CONSTRUCTION SITE
WEEK 3: August 31 - September 5 This week the earthwork will continue with the emphasis on building pad. The completion of the pad is expected by September 11. Also, preparation for the underground pipe work will begin.