Construction is now underway and should take approximately two weeks to complete. The benefits the East Taxiway Connector project brings is to provide direct access from the Taxiway to the new Apron and is designed to improve overall traffic flow to the Airport...
Blog
WMAA Receives Award
The West Michigan Regional Airport has been selected by the Michigan Department of Transportation (MDOT) Office of Aeronautics as the 2016 Michigan “Airport Sponsor of the Year” in the General Aviation Airport category. This award was recently presented at the 26th...
The WMAA Announces New Board Member
The West Michigan Airport Authority (WMAA) is pleased to announce the addition of Scott Corbin to the board. Appointed by the Holland City Council he currently serves as the Director of Emergency Management and Homeland Security for Allegan County and also as the...
BETH BLANTON WELCOMED AS NEW BOARD MEMBER
The new year brings new faces to the West Michigan Airport Authority board. One of the newest board members, Beth Blanton, will represent the City of Zeeland. Blanton is Director of Engagement at Lakeshore Advantage and is responsible for managing external events and...
WMRA Jet Float in Holland’s Parade of Lights
More than 75 entries illuminated Eighth Street to ring in the holidays on Tuesday night. The WMRA jet float was one of them with over 2,400 lights lighting up the float. The float was helping out Santa by bringing presents from the North Pole to our area. It was a...
Join us at the Holland Parade of Lights!
It's that time of year! The WMRA jet float will be joining over 80 entries when Santa arrives in downtown Holland on Tuesday, 6:30pm during the Parade of Lights. The jet, headed for the North Pole, will help Santa deliver presents around the world. Bring your family...
New Airport Business Center & Aircraft Apron Facts
Building: 7,500 square feet. The former office building was less than 2,000 square feet. Beautiful lobby and reception area furnished by Herman Miller. Main conference room furnished by Haworth, including glass walls. Pilot’s lounge furnished by Haworth, including...
WMRA Ribbon Cutting Ceremony
Held on October 13, the West Michigan Regional Airport Ribbon Cutting Ceremony for the new Business Center and Aircraft Apron project was a huge success. The first Ribbon Cutting was for the new Aircraft Apron Area and was held at the nose of a jet. Comments were made...
A WET & WILD RUNWAY 5K
A little rain didn't stop over 100 runners that showed up at West Michigan Regional Airport this past Saturday morning on August 24. Starting on the runway, they were here to run the Wings of Mercy Runway 5K held in conjunction with the Wings of Mercy CareAffaire....
WEEKS 50-52 WMRA CONSTRUCTION
LAST WEEKS 50-52: July 18 - August 6 BUILDING Installed lighting inverter Worked on antenna tower base Finish antenna installation Closeout documents SITE Punch list items
WEEKS 46-49 WMRA CONSTRUCTION SITE
WEEKS 46-49: June 20 – July 16 BUILDING Begin installation of radio tower Waiting for furniture Waiting for lighting inverter SITE Completed striping Completed fence installation
WEEKS 44-45 WMRA CONSTRUCTION SITE
WEEKS 44-45: June 6 – June 18 BUILDING Continued HVAC, electrical and plumbing Complete cabinets Complete installation of carpet Complete epoxy floor Complete painting Begin floor mats Install ramp railing Install glass door sidelights SITE Began P-501 repairs...