2 Week 12-13 bldgWEEK 12:  October 26-31
Site Improvements
Continued installation of geotextile fabric on apron, and installation of sand sub-base and aggregate base
Grading and compacting aggregate base for parking lot
Building
Completed underground plumbing, electrical and HVAC
Poured concrete floor

WEEK 13: November 2-7
Site Improvements
Continued installation of geotextile fabric, sand sub-base and aggregate base for apron
Paved the base course of asphalt (LVSP)on parking lot
Began the underground electrical on the landside of the building
Building
Steel erection