Month: August 2015
CONSTRUCTIVE LUNCHES
David Church, Technician at Crown Motors decided his lunch hour could be more constructive watching the construction happening at West Michigan Regional Airport. With the new Airport Office Building and Aircraft Apron project beginning on Tuesday, August 18 and Crown...
WEEK 2 SURVEYING AND SCRAPING
WEEK 2: August 24-28, 2015 Today the surveyors began staking a ditch that will be dug out and become the water management system on the site. The water on the site will drain into the ditch, be directed to a holding detention pond and eventually to the main ditch...
WEEK 1 BEGINNING OF A LONG-AWAITED PROJECT
WEEK 1: August 18-21, 2015 marked the first construction phase of the West Michigan Regional Airport’s new Business Center and Aircraft Apron project. “This is the long-awaited project that will enhance this airport's position as the primary access hub for economic...