WEEKS 22-23 WMRA CONSTRUCTION SITE

WEEKS 22-23:  January 4-16, 2016
BUILDING
Completed exterior and interior steel stud installation
Completed sheeting
Completed roofing for upper roof
Continued roofing for lower roof
Continued installation of window frames
Began mechanical, plumbing and electrical rough-in

WEEKS 20-21 WMRA CONSTRUCTION SITE

WEEKS 20-21:  December 21 – January 2, 2016
BUILDING
Finished exterior walls
Continue interior steel stud walls and sheeting
Installed roof penetration
Began installation of membrane roof
Began window frame installation