WEEKS 22-23 WMRA CONSTRUCTION SITE

3 WEEKS 22-23WEEKS 22-23:  January 4-16, 2016
BUILDING
Completed exterior and interior steel stud installation
Completed sheeting
Completed roofing for upper roof
Continued roofing for lower roof
Continued installation of window frames
Began mechanical, plumbing and electrical rough-in

12 WEEKS 22-23

10 WEEKS 22-23
9 WEEKS 22-23

8 WEEKS 2223

7 WEEKS 22-23

6 WEEKS 22-23
5 WEEKS 22-23

4 WEEKS 22-23

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more