West Michigan Airport Authority MISSION STATEMENT
To provide the public with state-of-the-art global air access to strengthen the local economy and improve the area’s quality of life.

West Michigan Airport Authority ACTION PLAN
Fiscal Year 2016 (July 1, 2015 – June 30, 2016)

1. New Airport Business Center:
a. Construct the Airport Business Center. ( Begin August 2015)
b. Construct the new apron. (Begin August 2015)
c. Move into the new Airport Business Center. (April 2016)
2. Remove the existing airport office building and, perhaps, a portion of this parking lot, and conduct site restoration for this airport entrance. (May 2016)
3. Evaluate the Authority staffing structure and revise as needed. (February 2016)
4. Provide a centralized location at the new Airport Business Center for all Airport Authority documents and reference materials. (May 2016)
5. Prepare a preliminary design, cost estimate and business plan for an additional public hangar building. (January 2016)
6. Prepare a crack sealing and paint marking program. (June 2016)
7. Revise the airport Stormwater Management Plan upon completion of the Airport Business Center and Apron projects if necessary. (June 2016)
8. Work with the Holland City Planning Commission on the preparation of an updated Master Plan for the area around the airport. (June 2016)
9. Communications:
a. Organize a ribbon cutting event for the new Airport Business Center.
b. Coordinate informational displays for the interior of the Airport Business Center.
c. Participate in at least three community events.
d. Distribute information on airport activities through videos, website updates, periodic newsletters, media releases and community presentations.
e. Continue to be active in social media venues such as Facebook and Twitter.
f. Provide updates to member units on activities of the Authority.
g. Interact with airport tenants and users on airport activities, needs and matters of interest.

West Michigan Airport Authority ACTION PLAN
Fiscal Year 2015 (July 1, 2014 – June 30, 2015)

1. New Airport Business Center
a. Complete property acquisition. (Complete in September 2014)
b. Prepare construction drawings for infrastructure. (Complete in October 2014)
c. Prepare construction drawings for apron. (Complete in October 2014)
d. Prepare construction drawings for the building. (Complete in October 2014)
e. Bid construction of the three construction projects. (December 2014)
f. Begin construction of the three projects. (March 2015)
2. Reorganize staff or work with another area organization to conduct Business Development activities at the airport. (July 2014)
3. Prepare a preliminary design, cost estimate and business plan for an additional public hangar building. (August 2014)
4. Evaluate options for maintenance of the Instrument Landing System and if it is decided to remain with the current maintenance provider, then update the agreement. (September 2014)
5. Evaluate the public T hangar lease rate, utility costs, maintenance needs and use of the hangars. (November 2014)
6. Interact on a more regular basis with public T hangar and land lease tenants to understand their needs and vision for the airport.
7. Review and update the Airport Emergency Plan. (September 2014)8. Prepare a crack sealing and paint marking program. (October 2014) a. Participate in at least three community events.b. Distribute information on airport activities through videos, website updates, periodic newsletters, media releases and community presentations.c. Continue to be active in social media venues such as Facebook and Twitter.
d. Provide updates to member units on activities of the Authority. (02.14.14)

 

West Michigan Airport Authority Approved ACTION PLAN
Fiscal Year 2014 (July 1, 2013 – June 30, 2014)

WMAA Approved Action Plan FY 2013-2014