WEEKS 26-27 WMRA CONSTRUCTION SITE

1aa Weeks 27-28WEEKS 26-27:  February 1-13, 2016
BUILDING
Completed roofing
North and east windows installed
Completed plumbing and electrical rough-in
Semco installed gas service
BPW installed power to building
Completed steel stud walls
Begin exterior wall insulation

 

1d Weeks 27-28

1ff Weeks 27-28

1b Weeks 27-28

3 a Weeks

10 Weeks a

5 Weeks a