Projects

EAST TAXIWAY CONNECTOR PROJECT

Construction is now underway and should take approximately two weeks to complete. The benefits the East Taxiway Connector project brings is to provide direct access from the Taxiway to the new Apron and is designed to improve overall traffic flow to the Airport Business Center.

Funding for the project is split between the FAA (90%) […]

New Airport Business Center & Aircraft Apron Facts

Building:
7,500 square feet. The former office building was less than 2,000 square feet.
Beautiful lobby and reception area furnished by Herman Miller.
Main conference room furnished by Haworth, including glass walls.
Pilot’s lounge furnished by Haworth, including glass walls.
East conference room furnished by Herman Miller.
Airport Authority staff work areas furnished by […]

WEEKS 50-52 WMRA CONSTRUCTION

LAST WEEKS 50-52:  July 18 – August 6

BUILDING
Installed lighting inverter
Worked on antenna tower base
Finish antenna installation
Closeout documents

SITE
Punch list items

 

 

 

 

WEEKS 46-49 WMRA CONSTRUCTION SITE

WEEKS 46-49: June 20 – July 16
BUILDING
Begin installation of radio tower
Waiting for furniture
Waiting for lighting inverter

SITE
Completed striping
Completed fence installation

 

 

 

 

WEEKS 44-45 WMRA CONSTRUCTION SITE

WEEKS 44-45: June 6 – June 18
BUILDING
Continued HVAC, electrical and plumbing
Complete cabinets
Complete installation of carpet
Complete epoxy floor
Complete painting
Begin floor mats
Install ramp railing
Install glass door sidelights

SITE
Began P-501 repairs
Continue apron paving
Begin seed and mulch
Begin paving the 2nd lift on the parking lot
Pour curb and gutter for islands
Topsoil and site clean-up

Save

WEEKS 42-43 WMRA CONSTRUCTION SITE

WEEKS 42-43: May 23 – June 4
BUILDING
Continued HVAC, electrical and plumbing
Began fin tube cabinets
Installed carpet
Complete painting
Continued installing cabinets
Complete metal siding
Installed more plumbing fixtures
Installed upper cabinets
Completed snow melt
Completed window flashing

SITE
Installed irrigation
Begin landscaping
Poured additional apron concrete
Poured sidewalks, curb and gutter
Saw cut and pour parking lot islands
Complete phase 1A including asphalt paving and electrical work

 

 

 

 

 

 

WEEKS 40-41 WMRA CONSTRUCTION SITE

WEEKS 40-41: May 9 – 21
BUILDING
Continued HVAC, electrical and plumbing
Continued metal siding
Continued installing cabinets
Completed window flashing
Installed bathroom fixtures
Installed acoustic ceiling tiles
Completed flag poles
Installed snowmelt in north sidewalk

SITE
Continued apron paving
Prep and pour sidewalks
Start work inside of TOFA

WEEKS 38-39 WMRA CONSTRUCTION SITE

WEEKS 38-39: April 25 – May 7
BUILDING
Began window flashing
Continued HVAC, electrical and plumbing
Continued metal siding
Continued cabinet installation
Continued painting
Completed acoustical ceiling grid
Completed ceiling clouds
Installed snowmelt in north sidewalk

SITE
Poured curb and gutter for cul-de-sac
Continued topsoiling
Sidewalk prep work
Concrete apron paving

    

WEEKS 36-37 WMRA CONSTRUCTION SITE

WEEKS 36-37:  April 11 – April 23
BUILDING
Continued HVAC, electrical and plumbing
Began siding
Began acoustic ceiling grid
Continue metal siding
Finish tile

SITE
Installed sub-base for cul-de-sac
Install aggregate
Continued paving concrete on apron
Sidewalk prep

WEEKS 34-35 WMRA CONSTRUCTION SITE

WEEKS 34-35:  March 28 – April 9
BUILDING
Continue HVAC, electrical work, plumbing
Start bathroom tile
Masonry work
Continue framing ceiling and installing ceiling grid
Installed bathroom cabinets and counters
Formed stairs and ramp and ran snow melt piping
Poured concrete for stairs and ramp
Finished hanging drywall and fireplace drywall

SITE IMPROVEMENTS
Continue excavation for cul-de-sac
Underdrain placement in cul-de-sac
Paved concrete on apron
Continued standing light […]