The West Michigan Regional Airport Authority is soliciting proposals to provide supplemental runway snow removal services for winter 2024-25. Contractors are expected to provide a summary of proposals to provide any or all of the following services outlined in the...
Projects
Wrapping Up Our FuturePREP’D and IChallengeU Summer 2024 Programs
The 2024 FuturePREP'D and IChallengeU summer programs successfully concluded at West Michigan Regional Airport! Students volunteered for these programs and chose to work with West Michigan Regional Airport as a business partner. Our...
WMRA Crack Sealant Maintenance
Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...
Stop by and visit the new WMRA terminal!
Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...
DEMOLITION DAY
Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...
Entryway Improvements at West Michigan Regional Airport
Because of the airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area was needed. The former airport terminal building at the entrance of Geurink Boulevard has served its purpose and is scheduled for demolition...
EAST TAXIWAY CONNECTOR PROJECT
Construction is now underway and should take approximately two weeks to complete. The benefits the East Taxiway Connector project brings is to provide direct access from the Taxiway to the new Apron and is designed to improve overall traffic flow to the Airport...
New Airport Business Center & Aircraft Apron Facts
Building: 7,500 square feet. The former office building was less than 2,000 square feet. Beautiful lobby and reception area furnished by Herman Miller. Main conference room furnished by Haworth, including glass walls. Pilot’s lounge furnished by Haworth, including...
WEEKS 50-52 WMRA CONSTRUCTION
LAST WEEKS 50-52: July 18 - August 6 BUILDING Installed lighting inverter Worked on antenna tower base Finish antenna installation Closeout documents SITE Punch list items
WEEKS 46-49 WMRA CONSTRUCTION SITE
WEEKS 46-49: June 20 – July 16 BUILDING Begin installation of radio tower Waiting for furniture Waiting for lighting inverter SITE Completed striping Completed fence installation
WEEKS 44-45 WMRA CONSTRUCTION SITE
WEEKS 44-45: June 6 – June 18 BUILDING Continued HVAC, electrical and plumbing Complete cabinets Complete installation of carpet Complete epoxy floor Complete painting Begin floor mats Install ramp railing Install glass door sidelights SITE Began P-501 repairs...
WEEKS 42-43 WMRA CONSTRUCTION SITE
WEEKS 42-43: May 23 - June 4 BUILDING Continued HVAC, electrical and plumbing Began fin tube cabinets Installed carpet Complete painting Continued installing cabinets Complete metal siding Installed more plumbing fixtures Installed upper cabinets Completed snow melt...