WEEKS 32-33 WMRA CONSTRUCTION SITE

3 WEEKS 32-33 032616

WEEKS 32-33:  March 14 – March 26
BUILDING
Continued HVAC and electrical
Continued drywall finishing
Continued priming/painting
Continued framing wood ceiling panels

SITE IMPROVEMENTS
Continued fine grading the apron
Poured parking lot and apron light bases