WEEK 3 OF WMRA CONSTRUCTION SITE

1 Week 3WEEK 3:  August 31 – September 5  This week the earthwork will continue with the emphasis on building pad. The completion of the pad is expected by September 11. Also, preparation for the underground pipe work will begin.

 

 

 