WEEKS 16-17 WMRA CONSTRUCTION SITE

1 week 16-17WEEKS 16-17:  November 23 – December 5
SITE IMPROVEMENTS
Begin and complete water main installation
Complete installation of P-209 aggregate base
Begin on cul-de-sac area
BUILDING
Continued steel erection
Continue steel stud walls
Begin steel sheeting
Begin steel decking

9 week 16-17

8 week 16-17

7 week 16-17

6 week 16-17

5 week 16-17

4 week 16-17

3 week 16-17

2 week 16-17

1 week 16-17

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more