WEEKS 16-17 WMRA CONSTRUCTION SITE

1 week 16-17WEEKS 16-17:  November 23 – December 5
SITE IMPROVEMENTS
Begin and complete water main installation
Complete installation of P-209 aggregate base
Begin on cul-de-sac area
BUILDING
Continued steel erection
Continue steel stud walls
Begin steel sheeting
Begin steel decking