WEEKS 10-11 WMRA CONSTRUCTION SITE

6 weeks 9-10WEEK 10:  October 19-24
Site Improvements
Continued installing geotextile fabric on apron, and installing sand sub-base and aggregate base.
Continued installing sand sub-base and aggregate base for parking lot.
Poured transformer pad for BPW transformer.
Poured Weir and overflow structure for detention pond outlet.


Building
Completed underground plumbing, electric and HVAC.
Installed planter drains and connected drains to apron underdrain.

Week 11: October 26-31
Site Improvements
Continued installing geotextile fabric, sand sub-base and aggregate base for apron.
Paved the base course of asphalt (LVSP) on parking lot.
Began the underground electrical on the land side of the building.
Began water main installation.
Building
Poured building floor.
Prepared for the arrival of steel structure members.

3 weeks 9-10 5 weeks 9-10 4 weeks 9-10 2 weeks 9-10 1 weeks 9-10 6 weeks 9-10