WEEKS 10-11 WMRA CONSTRUCTION SITE

6 weeks 9-10WEEK 10:  October 19-24
Site Improvements
Continued installing geotextile fabric on apron, and installing sand sub-base and aggregate base.
Continued installing sand sub-base and aggregate base for parking lot.
Poured transformer pad for BPW transformer.
Poured Weir and overflow structure for detention pond outlet.


Building
Completed underground plumbing, electric and HVAC.
Installed planter drains and connected drains to apron underdrain.

Week 11: October 26-31
Site Improvements
Continued installing geotextile fabric, sand sub-base and aggregate base for apron.
Paved the base course of asphalt (LVSP) on parking lot.
Began the underground electrical on the land side of the building.
Began water main installation.
Building
Poured building floor.
Prepared for the arrival of steel structure members.

3 weeks 9-10 5 weeks 9-10 4 weeks 9-10 2 weeks 9-10 1 weeks 9-10 6 weeks 9-10

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more