WEEKS 24-25 WMRA CONSTRUCTION SITE

1 Weeks 24-25WEEKS 24-25:  January 18-25, 2016
BUILDING
Completed roof
Completed roof drains
Poured concrete for fireplace wall
Finished plumbing and electrical rough in
Continued installation of window frames and windows
Begin HVAC and installation of glass
Install cable from transformer pad to building

3 Weeks 24-25

2 Weeks 24-25

5 Weeks 24-25

4 Weeks 24-25

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more