WEEKS 26-27 WMRA CONSTRUCTION SITE

1aa Weeks 27-28WEEKS 26-27:  February 1-13, 2016
BUILDING
Completed roofing
North and east windows installed
Completed plumbing and electrical rough-in
Semco installed gas service
BPW installed power to building
Completed steel stud walls
Begin exterior wall insulation

 

1d Weeks 27-28

1ff Weeks 27-28

1b Weeks 27-28

3 a Weeks

10 Weeks a

5 Weeks a

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more