WEEKS 28-29: February 15-27, 2016
BUILDING
Completed insulation and steel framing
Installed permanent power
Installed fireplace
Began gypsum board and drywall installation and masonry
Continued electrical work, plumbing and HVAC
(photo above includes WMAA Building & Development Committee members and representatives from Mead & Hunt, Progressive AE and CL Construction)