WEEKS 34-35 WMRA CONSTRUCTION SITE

1 weeks 34-35 040916WEEKS 34-35:  March 28 – April 9
BUILDING
Continue HVAC, electrical work, plumbing
Start bathroom tile
Masonry work
Continue framing ceiling and installing ceiling grid
Installed bathroom cabinets and counters
Formed stairs and ramp and ran snow melt piping
Poured concrete for stairs and ramp
Finished hanging drywall and fireplace drywall

SITE IMPROVEMENTS

Continue excavation for cul-de-sac
Underdrain placement in cul-de-sac
Paved concrete on apron
Continued standing light poles and fixtures
Completed electrical conduit installation
Completed fine grading the parking lot

2 weeks 34-35 040916 4 weeks 34-35 040916 5 weeks 34-35 040916 6 weeks 34-35 040916 7 weeks 34-35 040916 8 weeks 34-35 040916 9 weeks 34-35 040916

 

 

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more