WEEKS 36-37 WMRA CONSTRUCTION SITE

5 weeks 36-37WEEKS 36-37:  April 11 – April 23
BUILDING
Continued HVAC, electrical and plumbing
Began siding
Began acoustic ceiling grid
Continue metal siding
Finish tile

SITE
Installed sub-base for cul-de-sac
Install aggregate
Continued paving concrete on apron
Sidewalk prep

1 weeks 36-37

2 weeks 36-37

3 weeks 36-37

3a weeks 36-378

4 weeks 36-37

4a weeks 36-37