WEEKS 36-37 WMRA CONSTRUCTION SITE

5 weeks 36-37WEEKS 36-37:  April 11 – April 23
BUILDING
Continued HVAC, electrical and plumbing
Began siding
Began acoustic ceiling grid
Continue metal siding
Finish tile

SITE
Installed sub-base for cul-de-sac
Install aggregate
Continued paving concrete on apron
Sidewalk prep

1 weeks 36-37

2 weeks 36-37

3 weeks 36-37

3a weeks 36-378

4 weeks 36-37

4a weeks 36-37

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more