WEEKS 4 AND 5 OF WMRA CONSTRUCTION SITE

IMG_1184Week 4:  September 7 – 12 The construction crew continued earthwork balancing on both the Landside and Airside. The building pad was completed.

Week 5:  September 14 – 19 On September 15 Mead & Hunt was on site to stake building corners, the south detention pond, and the ditch from the south detention pond to the drain. The pipe crew worked on the storm sewer, sanitary sewer and watermain, and installed the undrain.

 

IMG_1191

 