WEEKS 4 AND 5 OF WMRA CONSTRUCTION SITE

IMG_1184Week 4:  September 7 – 12 The construction crew continued earthwork balancing on both the Landside and Airside. The building pad was completed.

Week 5:  September 14 – 19 On September 15 Mead & Hunt was on site to stake building corners, the south detention pond, and the ditch from the south detention pond to the drain. The pipe crew worked on the storm sewer, sanitary sewer and watermain, and installed the undrain.

 

IMG_1191

 

IMG_1210

 

IMG_1196

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more