WEEKS 40-41 WMRA CONSTRUCTION SITE

1 weeks 40-41

WEEKS 40-41: May 9 – 21
BUILDING
Continued HVAC, electrical and plumbing
Continued metal siding
Continued installing cabinets
Completed window flashing
Installed bathroom fixtures
Installed acoustic ceiling tiles
Completed flag poles
Installed snowmelt in north sidewalk

SITE
Continued apron paving
Prep and pour sidewalks
Start work inside of TOFA
3 weeks 40-42

4 weeks 40-41

5 weeks 40-41

6 weeks 40-41

7 weeks 40-41

8 weeks 40-41