WEEKS 42-43 WMRA CONSTRUCTION SITE

2 weeks 42-43WEEKS 42-43: May 23 – June 4
BUILDING
Continued HVAC, electrical and plumbing
Began fin tube cabinets
Installed carpet
Complete painting
Continued installing cabinets
Complete metal siding
Installed more plumbing fixtures
Installed upper cabinets
Completed snow melt
Completed window flashing

SITE
Installed irrigation
Begin landscaping
Poured additional apron concrete
Poured sidewalks, curb and gutter
Saw cut and pour parking lot islands
Complete phase 1A including asphalt paving and electrical work

3 weeks 42-43

 

 

 

 

 

 

4 weeks 42-43

5 weeks 42-43

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more