WEEKS 42-43 WMRA CONSTRUCTION SITE

2 weeks 42-43WEEKS 42-43: May 23 – June 4
BUILDING
Continued HVAC, electrical and plumbing
Began fin tube cabinets
Installed carpet
Complete painting
Continued installing cabinets
Complete metal siding
Installed more plumbing fixtures
Installed upper cabinets
Completed snow melt
Completed window flashing

SITE
Installed irrigation
Begin landscaping
Poured additional apron concrete
Poured sidewalks, curb and gutter
Saw cut and pour parking lot islands
Complete phase 1A including asphalt paving and electrical work

3 weeks 42-43

 

 

 

 

 

 

4 weeks 42-43

5 weeks 42-43