fbpx

WEEKS 44-45 WMRA CONSTRUCTION SITE

6 weeks 44-45WEEKS 44-45: June 6 – June 18
BUILDING
Continued HVAC, electrical and plumbing
Complete cabinets
Complete installation of carpet
Complete epoxy floor
Complete painting
Begin floor mats
Install ramp railing
Install glass door sidelights

SITE
Began P-501 repairs
Continue apron paving
Begin seed and mulch
Begin paving the 2nd lift on the parking lot
Pour curb and gutter for islands
Topsoil and site clean-up

1 weeks 44-453a weeks 44-45

4 weeks 44-455 weeks 44-45

Save

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more