WEEKS 6-7 OF WMRA CONSTRUCTION SITE

1 Weeks 6-7WEEK 6: September 21 – 26
Site improvements:
Completed storm sewer work
Installed under-drain in the parking lot and began working in apron under-drain
Installed weir structure for south detention pond
Building:
Began pouring concrete footings
Began pouring concrete walls

WEEK 7:  September 28 – October 10
Site improvements:
Poured remaining concrete walls
Building:

Completed under-drain installation for apron
Installed stabilizing fabric for apron sub-grade
Installed the first lift of sand sub-base for the apron

 