WEEKS 6-7 OF WMRA CONSTRUCTION SITE

1 Weeks 6-7WEEK 6: September 21 – 26
Site improvements:
Completed storm sewer work
Installed under-drain in the parking lot and began working in apron under-drain
Installed weir structure for south detention pond
Building:
Began pouring concrete footings
Began pouring concrete walls

WEEK 7:  September 28 – October 10
Site improvements:
Poured remaining concrete walls
Building:

Completed under-drain installation for apron
Installed stabilizing fabric for apron sub-grade
Installed the first lift of sand sub-base for the apron

 

2 Weeks 6-7

6 Weeks 6-7

 

5 Weeks 6-7

4 Weeks 6-7

 

3 Weeks 6-7

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more