WEEKS 8-9 OF WMRA CONSTRUCTION SITE

3 Weeks 8-9WEEK 8:  October 5-10
Site Improvements
Completed under-drain in the parking lot and apron
Began installation of Geotextile fabric on apron
Began installation sand sub-base for parking lot and apron
Building
Completed pouring foundation
Continued pouring concrete walls

WEEK 9: October 12-17
Site Improvements
Completed sub-base installation for parking lot and apron
Began installation of aggregate base
Electrical work began
Building
Poured remaining concrete walls
Began underground plumbing
Began back fill for flooring