WEEKS 8-9 OF WMRA CONSTRUCTION SITE

3 Weeks 8-9WEEK 8:  October 5-10
Site Improvements
Completed under-drain in the parking lot and apron
Began installation of Geotextile fabric on apron
Began installation sand sub-base for parking lot and apron
Building
Completed pouring foundation
Continued pouring concrete walls

WEEK 9: October 12-17
Site Improvements
Completed sub-base installation for parking lot and apron
Began installation of aggregate base
Electrical work began
Building
Poured remaining concrete walls
Began underground plumbing
Began back fill for flooring

1 Weeks 8-9

4 Weeks 8-9

5 Weeks 8-9

6 Weeks 8-9

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more