WEEKS 14-15 WMRA CONSTRUCTION SITE

2 week 14-15WEEK 14:  November 9-14
Site Improvements
Continued on sanitary sewer installation
Worked on compaction of the sub-base material for the apron
Began restoration of areas requiring MDOT roadside mix
Building
Continued steel construction

WEEK 15: November 16-21
Site Improvements
Completed sanitary sewer
Installed 8″ PVC storm for roof drains
Began water main installation
Installed 8″ PVC storm for roof drains
Began on Cul-de-Sac area
Building
Continued steel erection
Begin steel stud walls