WEEKS 14-15 WMRA CONSTRUCTION SITE

2 week 14-15WEEK 14:  November 9-14
Site Improvements
Continued on sanitary sewer installation
Worked on compaction of the sub-base material for the apron
Began restoration of areas requiring MDOT roadside mix
Building
Continued steel construction

WEEK 15: November 16-21
Site Improvements
Completed sanitary sewer
Installed 8″ PVC storm for roof drains
Began water main installation
Installed 8″ PVC storm for roof drains
Began on Cul-de-Sac area
Building
Continued steel erection
Begin steel stud walls

3 week 14-15 4 week 14-15 5 week 14-15 6 week 14-15 7 week 14-15 8 week 14-15 9 week 14-15 10 week 14-15

Recent & Related

WMRA Crack Sealant Maintenance

Crack Sealant is an important part of maintaining the overall pavement surface at West Michigan Regional Airport. (Check out the video that follows.) Over time, pavement will deteriorate due to weather and stress. Crack Sealant is used to help get many more years...

read more

Stop by and visit the new WMRA terminal!

Completed in 2017, the new 7,500 square foot building hosts a beautiful lobby and reception area with all furnishings donated by Herman Miller and Haworth. The main conference room is a great place that can be reserved by local businesses and organizations for...

read more

DEMOLITION DAY

Because of the West Michigan Regional Airport's growth, a much larger and newer facility that reflected the economic health and vitality of the area replaced the former airport terminal building at the entrance of Geurink Boulevard. Ron and Linda Ludema used the ranch...

read more