WEEKS 28-29 WMRA CONSTRUCTION SITE

WEEKS 28-29:  February 15-27, 2016
BUILDING
Completed insulation and steel framing
Installed permanent power
Installed fireplace
Began gypsum board and drywall installation and masonry
Continued electrical work, plumbing and HVAC

(photo above includes WMAA Building & Development Committee members and representatives from Mead & Hunt, Progressive AE and CL Construction)

Committee Tours New Business Center

The WMAA Building & Development Committee toured the new Airport Business Center. Committee members were excited to see the progress made. To date the roofing has been completed including the plumbing, electrical rough-in and steel stud walls. Semco installed gas service and the BPW installed power to the building. Check the WMRA website weekly […]

WEEKS 26-27 WMRA CONSTRUCTION SITE

WEEKS 26-27:  February 1-13, 2016
BUILDING
Completed roofing
North and east windows installed
Completed plumbing and electrical rough-in
Semco installed gas service
BPW installed power to building
Completed steel stud walls
Begin exterior wall insulation

 

WEEKS 24-25 WMRA CONSTRUCTION SITE

WEEKS 24-25:  January 18-25, 2016
BUILDING
Completed roof
Completed roof drains
Poured concrete for fireplace wall
Finished plumbing and electrical rough in
Continued installation of window frames and windows
Begin HVAC and installation of glass
Install cable from transformer pad to building