WEEKS 28-29 WMRA CONSTRUCTION SITE

WEEKS 28-29:  February 15-27, 2016 BUILDING Completed insulation and steel framing Installed permanent power Installed fireplace Began gypsum board and drywall installation and masonry Continued electrical work, plumbing and HVAC (photo above includes WMAA Building...

read more

Committee Tours New Business Center

The WMAA Building & Development Committee toured the new Airport Business Center. Committee members were excited to see the progress made. To date the roofing has been completed including the plumbing, electrical rough-in and steel stud walls. Semco installed gas...

read more

WEEKS 26-27 WMRA CONSTRUCTION SITE

WEEKS 26-27:  February 1-13, 2016 BUILDING Completed roofing North and east windows installed Completed plumbing and electrical rough-in Semco installed gas service BPW installed power to building Completed steel stud walls Begin exterior wall insulation  

read more

WEEKS 24-25 WMRA CONSTRUCTION SITE

WEEKS 24-25:  January 18-25, 2016 BUILDING Completed roof Completed roof drains Poured concrete for fireplace wall Finished plumbing and electrical rough in Continued installation of window frames and windows Begin HVAC and installation of glass Install cable from...