fbpx

Blog

WEEKS 34-35 WMRA CONSTRUCTION SITE

WEEKS 34-35:  March 28 - April 9 BUILDING Continue HVAC, electrical work, plumbing Start bathroom tile Masonry work Continue framing ceiling and installing ceiling grid Installed bathroom cabinets and counters Formed stairs and ramp and ran snow melt piping Poured...

read more

WEEKS 32-33 WMRA CONSTRUCTION SITE

WEEKS 32-33:  March 14 – March 26 BUILDING Continued HVAC and electrical Continued drywall finishing Continued priming/painting Continued framing wood ceiling panels SITE IMPROVEMENTS Continued fine grading the apron Poured parking lot and apron light bases

read more

WEEKS 30-31 WMRA CONSTRUCTION SITE

WEEKS 30-31:  February 29 - March 12 BUILDING Continue drywall installation Continue masonry Continue HVAC and electrical Install Suntuitive Glass Continue electrical work Installed fireplace  

read more

2016 WINGS OF MERCY CAREAFFAIRE

Please join us on Saturday, August 27, 8:00 a.m. - 12 noon for the 2016 Holland Wings of Mercy CareAffaire at West Michigan Regional Airport. To register for the Wings of Mercy Runway 5K, use the following link: Wings of Mercy Family fun include a fly-in, delicious...

read more

ENERGY SAVING WINDOWS BEING INSTALLED AT WMRA

Pleotint, whose corporate  headquarters and manufacturing are located in Jension, is all about saving energy. The low-e glass which allows visible light to pass through while controlling the passage of solar heat is now being installed at the new WMRA Business Center....

read more

WEEKS 28-29 WMRA CONSTRUCTION SITE

WEEKS 28-29:  February 15-27, 2016 BUILDING Completed insulation and steel framing Installed permanent power Installed fireplace Began gypsum board and drywall installation and masonry Continued electrical work, plumbing and HVAC (photo above includes WMAA Building...

read more

Committee Tours New Business Center

The WMAA Building & Development Committee toured the new Airport Business Center. Committee members were excited to see the progress made. To date the roofing has been completed including the plumbing, electrical rough-in and steel stud walls. Semco installed gas...

read more

WEEKS 26-27 WMRA CONSTRUCTION SITE

WEEKS 26-27:  February 1-13, 2016 BUILDING Completed roofing North and east windows installed Completed plumbing and electrical rough-in Semco installed gas service BPW installed power to building Completed steel stud walls Begin exterior wall insulation  

read more

WEEKS 24-25 WMRA CONSTRUCTION SITE

WEEKS 24-25:  January 18-25, 2016 BUILDING Completed roof Completed roof drains Poured concrete for fireplace wall Finished plumbing and electrical rough in Continued installation of window frames and windows Begin HVAC and installation of glass Install cable from...

read more

WEEKS 22-23 WMRA CONSTRUCTION SITE

WEEKS 22-23:  January 4-16, 2016 BUILDING Completed exterior and interior steel stud installation Completed sheeting Completed roofing for upper roof Continued roofing for lower roof Continued installation of window frames Began mechanical, plumbing and electrical...

read more

WEEKS 20-21 WMRA CONSTRUCTION SITE

WEEKS 20-21:  December 21 - January 2, 2016 BUILDING Finished exterior walls Continue interior steel stud walls and sheeting Installed roof penetration Began installation of membrane roof Began window frame installation Began mechanical, plumbing and electrical...

read more

WEEKS 18-19 WMRA CONSTRUCTION SITE

WEEKS 18-19:  December 7 - December 19 BUILDING Continue with steel stud walls and sheeting Install roof drains Begin installation of membrane roof Begin work on brick and window frames

read more