fbpx

Projects

WEEKS 36-37 WMRA CONSTRUCTION SITE

WEEKS 36-37:  April 11 – April 23 BUILDING Continued HVAC, electrical and plumbing Began siding Began acoustic ceiling grid Continue metal siding Finish tile SITE Installed sub-base for cul-de-sac Install aggregate Continued paving concrete on apron Sidewalk prep

read more

WEEKS 34-35 WMRA CONSTRUCTION SITE

WEEKS 34-35:  March 28 - April 9 BUILDING Continue HVAC, electrical work, plumbing Start bathroom tile Masonry work Continue framing ceiling and installing ceiling grid Installed bathroom cabinets and counters Formed stairs and ramp and ran snow melt piping Poured...

read more

WEEKS 32-33 WMRA CONSTRUCTION SITE

WEEKS 32-33:  March 14 – March 26 BUILDING Continued HVAC and electrical Continued drywall finishing Continued priming/painting Continued framing wood ceiling panels SITE IMPROVEMENTS Continued fine grading the apron Poured parking lot and apron light bases

read more

WEEKS 30-31 WMRA CONSTRUCTION SITE

WEEKS 30-31:  February 29 - March 12 BUILDING Continue drywall installation Continue masonry Continue HVAC and electrical Install Suntuitive Glass Continue electrical work Installed fireplace  

read more

WEEKS 28-29 WMRA CONSTRUCTION SITE

WEEKS 28-29:  February 15-27, 2016 BUILDING Completed insulation and steel framing Installed permanent power Installed fireplace Began gypsum board and drywall installation and masonry Continued electrical work, plumbing and HVAC (photo above includes WMAA Building...

read more

WEEKS 26-27 WMRA CONSTRUCTION SITE

WEEKS 26-27:  February 1-13, 2016 BUILDING Completed roofing North and east windows installed Completed plumbing and electrical rough-in Semco installed gas service BPW installed power to building Completed steel stud walls Begin exterior wall insulation  

read more

WEEKS 24-25 WMRA CONSTRUCTION SITE

WEEKS 24-25:  January 18-25, 2016 BUILDING Completed roof Completed roof drains Poured concrete for fireplace wall Finished plumbing and electrical rough in Continued installation of window frames and windows Begin HVAC and installation of glass Install cable from...

read more

WEEKS 22-23 WMRA CONSTRUCTION SITE

WEEKS 22-23:  January 4-16, 2016 BUILDING Completed exterior and interior steel stud installation Completed sheeting Completed roofing for upper roof Continued roofing for lower roof Continued installation of window frames Began mechanical, plumbing and electrical...

read more

WEEKS 20-21 WMRA CONSTRUCTION SITE

WEEKS 20-21:  December 21 - January 2, 2016 BUILDING Finished exterior walls Continue interior steel stud walls and sheeting Installed roof penetration Began installation of membrane roof Began window frame installation Began mechanical, plumbing and electrical...

read more

WEEKS 18-19 WMRA CONSTRUCTION SITE

WEEKS 18-19:  December 7 - December 19 BUILDING Continue with steel stud walls and sheeting Install roof drains Begin installation of membrane roof Begin work on brick and window frames

read more

WEEKS 16-17 WMRA CONSTRUCTION SITE

WEEKS 16-17:  November 23 - December 5 SITE IMPROVEMENTS Begin and complete water main installation Complete installation of P-209 aggregate base Begin on cul-de-sac area BUILDING Continued steel erection Continue steel stud walls Begin steel sheeting Begin steel...

read more

WEEKS 14-15 WMRA CONSTRUCTION SITE

WEEK 14:  November 9-14 Site Improvements Continued on sanitary sewer installation Worked on compaction of the sub-base material for the apron Began restoration of areas requiring MDOT roadside mix Building Continued steel construction WEEK 15: November 16-21 Site...

read more