Projects

WEEKS 40-41 WMRA CONSTRUCTION SITE

WEEKS 40-41: May 9 – 21
BUILDING
Continued HVAC, electrical and plumbing
Continued metal siding
Continued installing cabinets
Completed window flashing
Installed bathroom fixtures
Installed acoustic ceiling tiles
Completed flag poles
Installed snowmelt in north sidewalk

SITE
Continued apron paving
Prep and pour sidewalks
Start work inside of TOFA

WEEKS 38-39 WMRA CONSTRUCTION SITE

WEEKS 38-39: April 25 – May 7
BUILDING
Began window flashing
Continued HVAC, electrical and plumbing
Continued metal siding
Continued cabinet installation
Continued painting
Completed acoustical ceiling grid
Completed ceiling clouds
Installed snowmelt in north sidewalk

SITE
Poured curb and gutter for cul-de-sac
Continued topsoiling
Sidewalk prep work
Concrete apron paving

    

WEEKS 36-37 WMRA CONSTRUCTION SITE

WEEKS 36-37:  April 11 – April 23
BUILDING
Continued HVAC, electrical and plumbing
Began siding
Began acoustic ceiling grid
Continue metal siding
Finish tile

SITE
Installed sub-base for cul-de-sac
Install aggregate
Continued paving concrete on apron
Sidewalk prep

WEEKS 34-35 WMRA CONSTRUCTION SITE

WEEKS 34-35:  March 28 – April 9
BUILDING
Continue HVAC, electrical work, plumbing
Start bathroom tile
Masonry work
Continue framing ceiling and installing ceiling grid
Installed bathroom cabinets and counters
Formed stairs and ramp and ran snow melt piping
Poured concrete for stairs and ramp
Finished hanging drywall and fireplace drywall

SITE IMPROVEMENTS
Continue excavation for cul-de-sac
Underdrain placement in cul-de-sac
Paved concrete on apron
Continued standing light […]

WEEKS 32-33 WMRA CONSTRUCTION SITE

WEEKS 32-33:  March 14 – March 26
BUILDING
Continued HVAC and electrical
Continued drywall finishing
Continued priming/painting
Continued framing wood ceiling panels

SITE IMPROVEMENTS
Continued fine grading the apron
Poured parking lot and apron light bases

WEEKS 30-31 WMRA CONSTRUCTION SITE

WEEKS 30-31:  February 29 – March 12
BUILDING
Continue drywall installation
Continue masonry
Continue HVAC and electrical
Install Suntuitive Glass
Continue electrical work
Installed fireplace
 

WEEKS 28-29 WMRA CONSTRUCTION SITE

WEEKS 28-29:  February 15-27, 2016
BUILDING
Completed insulation and steel framing
Installed permanent power
Installed fireplace
Began gypsum board and drywall installation and masonry
Continued electrical work, plumbing and HVAC

(photo above includes WMAA Building & Development Committee members and representatives from Mead & Hunt, Progressive AE and CL Construction)

WEEKS 26-27 WMRA CONSTRUCTION SITE

WEEKS 26-27:  February 1-13, 2016
BUILDING
Completed roofing
North and east windows installed
Completed plumbing and electrical rough-in
Semco installed gas service
BPW installed power to building
Completed steel stud walls
Begin exterior wall insulation

 

WEEKS 24-25 WMRA CONSTRUCTION SITE

WEEKS 24-25:  January 18-25, 2016
BUILDING
Completed roof
Completed roof drains
Poured concrete for fireplace wall
Finished plumbing and electrical rough in
Continued installation of window frames and windows
Begin HVAC and installation of glass
Install cable from transformer pad to building

WEEKS 22-23 WMRA CONSTRUCTION SITE

WEEKS 22-23:  January 4-16, 2016
BUILDING
Completed exterior and interior steel stud installation
Completed sheeting
Completed roofing for upper roof
Continued roofing for lower roof
Continued installation of window frames
Began mechanical, plumbing and electrical rough-in