Projects

WEEKS 20-21 WMRA CONSTRUCTION SITE

WEEKS 20-21:  December 21 – January 2, 2016
BUILDING
Finished exterior walls
Continue interior steel stud walls and sheeting
Installed roof penetration
Began installation of membrane roof
Began window frame installation
Began mechanical, plumbing and electrical rough-in

 

WEEKS 18-19 WMRA CONSTRUCTION SITE

WEEKS 18-19:  December 7 – December 19
BUILDING
Continue with steel stud walls and sheeting
Install roof drains
Begin installation of membrane roof
Begin work on brick and window frames

WEEKS 16-17 WMRA CONSTRUCTION SITE

WEEKS 16-17:  November 23 – December 5
SITE IMPROVEMENTS
Begin and complete water main installation
Complete installation of P-209 aggregate base
Begin on cul-de-sac area
BUILDING
Continued steel erection
Continue steel stud walls
Begin steel sheeting
Begin steel decking

WEEKS 14-15 WMRA CONSTRUCTION SITE

WEEK 14:  November 9-14
Site Improvements
Continued on sanitary sewer installation
Worked on compaction of the sub-base material for the apron
Began restoration of areas requiring MDOT roadside mix
Building
Continued steel construction […]

WEEKS 12-13 WMRA CONSTRUCTION SITE

WEEK 12:  October 26-31
Site Improvements
Continued installation of geotextile fabric on apron, and installation of sand sub-base and aggregate base
Grading and compacting aggregate base for parking lot
Building
Completed underground plumbing, electrical and HVAC
Poured concrete floor […]

WEEKS 10-11 WMRA CONSTRUCTION SITE

WEEK 10:  October 19-24
Site Improvements
Continued installing geotextile fabric on apron, and installing sand sub-base and aggregate base.
Continued installing sand sub-base and aggregate base for parking lot.
Poured transformer pad for BPW transformer.
Poured Weir and overflow structure for detention pond outlet.

[…]

WEEKS 8-9 OF WMRA CONSTRUCTION SITE

WEEK 8:  October 5-10
Site Improvements
Completed under-drain in the parking lot and apron
Began installation of Geotextile fabric on apron
Began installation sand sub-base for parking lot and apron
Building
Completed pouring foundation
Continued pouring concrete walls

WEEK 9: October 12-17
Site Improvements
Completed sub-base installation for parking lot and apron
Began installation of aggregate base
Electrical work began
Building
Poured remaining concrete walls
Began underground plumbing
Began back […]

WEEKS 6-7 OF WMRA CONSTRUCTION SITE

WEEK 6: September 21 – 26
Site improvements:
Completed storm sewer work
Installed under-drain in the parking lot and began working in apron under-drain
Installed weir structure for south detention pond
Building:
Began pouring concrete footings
Began pouring concrete walls

WEEK 7:  September 28 – October 10
Site improvements:
Poured remaining concrete walls
Building:
Completed under-drain installation for apron
Installed stabilizing fabric for apron sub-grade
Installed the first […]

WEEKS 4 AND 5 OF WMRA CONSTRUCTION SITE

Week 4:  September 7 – 12 The construction crew continued earthwork balancing on both the Landside and Airside. The building pad was completed.

Week 5:  September 14 – 19 On September 15 Mead & Hunt was on site to stake building corners, the south detention pond, and the ditch from the south detention pond to […]

WEEK 3 OF WMRA CONSTRUCTION SITE

WEEK 3:  August 31 – September 5  This week the earthwork will continue with the emphasis on building pad. The completion of the pad is expected by September 11. Also, preparation for the underground pipe work will begin.